Sector Check: Power | The grid can’t wait, and the power plants are late

This article is a summary of the subscriber piece published on October 15, 2026. Figures and price targets are available in the original.

Buongiorno, readers.

I have finally run a check on power, a sector I had not covered for a long time. Demand keeps climbing while new power plants arrive late, and I will also explain why I stayed away on purpose.


Looking back at three pieces

I wrote about power in depth three times this year.

  • January 14, “Harder to get than GPUs: Big Tech’s race for power and the winners.” I split the US power shortage by time horizon. Fuel cells (devices that make electricity from gas through a chemical reaction rather than burning it), which can be installed fast, for right now. Gas turbines and reciprocating engines (large piston engines) for the next two to five years. Nuclear and small modular reactors (SMRs) after that.
  • March 26, “I read all 200 pages of the EIA outlook: solar plus storage is right, and the market missed a layer.” I looked at the parts and systems that connect solar and energy storage systems (ESS) to the grid, and picked Shoals Technologies (SHLS US) and Fluence Energy (FLNC US) as names the market had not yet priced in.
  • April 11, “The battery that became a power plant: inside the ESS value chain.” I named transformers as the bottleneck that would last longest, and within that, Sanil Electric (062040 KS).

Nine months later, this is how those calls look.

  • The picture of gas carrying AI power was right. Where the money arrived first was not what I expected. In January I wrote that gas turbines took two to four years to deliver (the lead time from order to delivery). Order books now run past that, into 2029-2030 production. But profits came first to reciprocating engine and fuel cell makers, and to companies that already own gas plants, more than to the large turbine makers. Once turbines jammed, the money seems to have gone first to whatever could route around the jam.
  • Reciprocating engines, my January workaround, were the most accurate call. Back then I only listed Finnish, German and British makers. Now Korean companies have taken a place in this market. That was the standout finding of this check, and I come back to it below.
  • Shoals and Sanil Electric both more than doubled at one point. Shoals went from $6.0 when I wrote about it to $12.77 in early June. Sanil Electric went from KRW 134,000 to KRW 333,500 in early May (closing prices). I wrote at the time that Sanil Electric had run too far and that it was time to harvest, that is, to take profits. Both are now more than 30% off their highs. Even so, Shoals sits a little over 40% above where it was when I wrote, and Sanil Electric close to 60% above. The three Korean makers of extra-high-voltage transmission transformers, by contrast, fell sharply.
  • Fluence did not work out. I already recorded that call as wrong in my September 17 company check. November results are the last checkpoint.

I did not come back to power until now for a reason. Power mattered as much as ever, but valuations across the sector (how richly share prices were set against earnings) were too high. At those prices I did not think I could introduce either the transformer makers or the power generation names. Korean transformer makers were the clearest case. Their profits were already very high, and they were entering a stretch where growth would slow relative to what the market expected. A correction looked due. And in fact, as Korean stocks corrected from late June, HD Hyundai Electric (267260 KS) fell more than 40%, Hyosung Heavy Industries (298040 KS) more than 35%, and LS ELECTRIC (010120 KS) close to 25% by October 13.

So this time I started with the market rather than the stocks. First, what is actually happening in power because there is not enough of it.


What is happening in power right now

In one line: the buyers of electricity are lining up, and the equipment to make it cannot keep up. Buyers have started managing the supply chain themselves, and the market has grown more doubtful about when data centers will actually switch on.

Big Tech is buying power directly. Constellation Energy (CEG US), the largest nuclear owner in the US, signed 20-year power supply contracts with Amazon on September 30 and with Google on October 6. In early October, the US Department of Energy announced a conditional commitment to lend up to $4.2 billion to raise output at three Vistra (VST US) nuclear plants.

Generating equipment is short. In September, GE Aerospace agreed to buy CPP, a company that casts gas turbine blades, for $11.7 billion, and Elon Musk said he would build a plant in Texas to make those blades himself. The users of turbines have started managing even the parts factories.

Data centers are waiting for power. In September, part of an Oracle data center in Wisconsin declared force majeure (a situation where a contract cannot be honored). The gas pipeline that was supposed to feed its power plant was late. Dominion Energy, the Virginia utility, dropped 19GW of its 54GW in grid connection requests from its plans. 1GW is roughly what one large nuclear reactor produces. The market has started asking whether announced data centers will actually get built.

The nuclear plants under these contracts will not add power until 2028 or later. Until then, gas is filling the gap. So I broke down, step by step, how gas becomes electricity.


From one molecule of gas to electricity

How gas becomes power: four steps from fuel to the grid

Gas goes through four steps on its way to becoming electricity. The gas turbine is just one of several machines in the second step.

First, fuel. This step moves gas to the power plant. US pipeline construction is at its busiest in 20 years, but projects are often held up by permits and lawsuits. The Oracle case above got stuck here.

Second, conversion. These are the machines that turn gas into electricity: large gas turbines, reciprocating engines, fuel cells and small turbines. The most blocked is the large gas turbine. Global orders stand at 110GW, while the industry can build 60-70GW a year, and prices are close to three times their 2019 level.

The hardest turbine part to make is the blade. It has to withstand heat above 1,000 degrees Celsius, and only three or four plants in the world can cast blades in volume (pouring molten metal into molds). That is why GE Aerospace and Musk reached for those plants.

As turbines became hard to get, data centers started running many reciprocating engines side by side. HD Hyundai Heavy Industries (329180 KS) signed data center power engine contracts of 684MW in April and 1GW in August (1,000MW makes 1GW), and in September decided to build a 3GW land-based engine plant in Ulsan, due for completion in May 2028. This is the route I listed as a workaround in January, and a Korean company has now stepped onto it.

As engines multiplied, supply tightened inside the engine itself: the turbocharger. It uses the force of the exhaust to push more air into the engine and raise its output. Accelleron (ACLN SW), the world leader in turbochargers, said first-half sales for high-speed engines grew around 40%, and deliveries for US data center power more than doubled. The bottleneck is moving from turbines to engines, and from engines to their parts.

The engine route to power: from reciprocating engines to turbochargers

Third, efficiency. This step makes more electricity from the same gas. A gas turbine running alone turns only about a third of the fuel’s heat into electricity. Capture the exhaust heat in a heat recovery steam generator (HRSG) and spin a steam turbine with it, and that share rises to close to 60%. This equipment goes into large combined-cycle plants that run gas and steam turbines together. If a data center chooses engines or fuel cells, it is not needed. Steam turbines are not a bottleneck.

Fourth, existing plants. The harder it is to build new capacity, the more the gas plants already running, and their maintenance, are worth. As my April piece showed, in 2025 the US added 3.8 times as much battery capacity as new gas capacity, and planned battery additions for 2026 exceed 24GW. Batteries are backing up the existing gas fleet.

Wherever in these four steps the electricity is made, it reaches the grid through a transformer. Whether turbines, engines or fuel cells grow, transformers are needed.

So where do the share prices of the companies at each step stand today? Some have run ahead of their profits, and some have not caught up yet.


Where the companies stand

I will follow the same order as the steps above, starting with the second step: the companies that turn gas into electricity. Even within one step, the timing of when orders become profit, and how far the share price has run ahead, differs by company.

Doosan Enerbility (034020 KS). Gas turbine orders came in as I described in January. It won 12 units from US Big Tech, and seven 380MW-class units will ship from 2029. Including nuclear main equipment (core components such as reactor vessels), its order backlog (work won but not yet booked as revenue) is KRW 27.5 trillion. But this work only turns into profit from the first quarter of next year, and costs come first until then. The first check is whether gas turbine operating profit in the third quarter, reported in early November, keeps pace with the company’s second-half target.

GE Vernova (GEV US) and Caterpillar (CAT US) are in a different place. GE Vernova’s turbines sold at higher prices will be delivered in 2027-28, and Caterpillar’s engines for power generation and gas compression are in tight supply. Even so, I judge that both share prices already carry profits several years out.

HD Hyundai Marine Engine (071970 KS). It is known as a ship engine maker, but it sits on both supply bottlenecks described above: turbochargers, which the demand that routed around turbines into engines now needs, and gas turbine blades, the tightest part of the turbine itself.

  • According to its half-year report, power turbocharger output went from 96 units in 2024 to 180 in 2025 and 254 in the first half of this year. That is close to a threefold pace in a year, and plant utilization is around 85%. But turbochargers are still only part of the parts division, which is a little over 20% of sales.
  • At its September earnings call, the company laid out turbocharger expansion in two stages: existing capacity in mid-2027, and a new plant in mid-2028. The new plant’s timing lines up with the completion of HD Hyundai Heavy Industries’ land engine plant.
  • It has delivered more than 70 gas turbine blades to Doosan Enerbility, with qualification results due in the second half.

More engine orders call for turbochargers; more turbine orders call for blades. Whichever route power capacity takes, it looks set to reach this company’s order book. The open question is that both businesses are still a small share of total sales.

Bloom Energy (BE US). This is the fuel cell maker I listed in January as the power source that can go in fastest, and as that picture suggested, its profits arrived first. Shipments for hyperscalers (large cloud companies) have been turning into revenue since the second quarter, and it signed a supply agreement with Oracle for up to 2.8GW (1.2GW initially). Oracle’s large data center project, Jupiter, slipped to early 2027 because of pipeline permit delays, but Oracle reconfirmed its volume intent at the end of September. The concern is just as clear: 73% of first-half revenue came from one customer. With third-quarter results on October 22, the questions were whether revenue would meet my estimate and whether the delivery timing for Jupiter’s initial volume would be disclosed.

In the third step, efficiency equipment, profits also run on different clocks.

BHI (083650 KS) and MICO (059090 KS). Both make heat recovery steam generators (HRSGs), but their profits arrive at different times.

  • BHI’s operating margin (operating profit as a share of revenue) has risen into the 15% range as Middle East orders turn into revenue. Its backlog is KRW 2.5 trillion, and it added KRW 440 billion of orders in the third quarter.
  • MICO, through its subsidiary HPS, completed the acquisition of NEM Energy on September 9. The Dutch company has won more HRSG orders than anyone since 1980. HRSG demand from large US combined-cycle plants will come from plants that start running in 2028 or later, so profits will arrive later than at BHI. Most of MICO’s market value is explained by its stake in subsidiary KOMICO, and the path from NEM’s profits to MICO shareholders is complicated.

For existing plants and nuclear, the contracts have run ahead of the profits.

Vistra. This year, profits rose as grid capacity prices (what grid operators pay to keep generating capacity on standby for shortages) increased and power sold forward was recontracted at new prices. In the first half of next year, profit growth slows sharply. The Department of Energy loan commitment becomes a formal contract only once conditions are met, and the 433MW of new output arrives only in the early 2030s.

Constellation Energy. The Google and Amazon contracts are signed, but the added nuclear output arrives in 2028 or later. The contract news went into the price first.

Cameco (CCJ US). Hopes for a listing of its subsidiary Westinghouse have already gone into the share price.

KEPCO Engineering & Construction (052690 KS). This company draws the blueprints for nuclear plants. Design starts before construction, so it is the first spot in the nuclear chain to get paid. But the numbers are still slow. Only a little over 3% of the design contract for the Dukovany plant in the Czech Republic had become revenue by the end of the first half, and second-quarter revenue was slightly lower than a year earlier. Korea’s new domestic reactors and the Korea-US nuclear cooperation do not yet have design contracts with the company. On the design side too, I judge that the share price has run ahead of profits.

Transformers split into two markets, as I laid out in April: extra-high-voltage transformers for transmission grids (HD Hyundai Electric, Hyosung Heavy Industries, LS ELECTRIC) and special distribution transformers for ESS and data centers (Sanil Electric). This decline was concentrated in extra-high voltage.

  • HD Hyundai Electric. The next check is whether it holds an operating margin of around 26% in the third quarter despite currency headwinds.
  • Hyosung Heavy Industries. Profits on units built early to avoid US anti-dumping duties (extra tariffs on imports judged to be priced unfairly low) land in the fourth quarter. The next step is starting up its gas-insulated switchgear (GIS, equipment that connects and cuts power) plant in Changwon.
  • LS ELECTRIC. Its share price already includes profits far into the future, in my view.
  • Sanil Electric. It has fallen more than 35% from its early-May high. It announced a KRW 35.1 billion supply contract for ESS transformers on October 6, and another expansion or a larger order is the next thing to watch.

I looked at Powell Industries (POWL US), a US maker of distribution equipment and switchgear (gear that splits and cuts electrical power), for comparison. Its backlog grew close to 70% in a year, but the share price already reflects earnings at the 2028 level.

In solar, a US minimum price on imported polysilicon ($21 per kg) takes effect on December 4. Solar panels are made by melting polysilicon into ingots and wafers, which then become cells and modules.

OCI Holdings (010060 KS). It makes polysilicon, the very first step in the process, at its Malaysian subsidiary. Sales held back while the market waited for the minimum price are coming back from the third quarter, and I expect contracts signed at the new price to feed into profits from the first quarter of next year. Its long-term supply volume is already sold out. The first check is whether third-quarter polysilicon sales exceed 6,000 tons.

Hanwha Solutions (009830 KS). It sits in the same US solar supply chain, making cells and modules. Its Cartersville, Georgia plant started ingot and wafer production early this year and completed its cell plant in June, and it is now ramping output. The company said the US advanced manufacturing production credit (AMPC) would rise to about KRW 230 billion in the third quarter and about KRW 310 billion in the fourth. My read is that the third quarter carries the heaviest fixed cost from the cell plant, and from the fourth quarter the increase in tax credits outweighs that burden.

Shoals Technologies. It makes the wiring and connectors for solar plants. In March I argued that “profits were held down by tariffs and plant relocation costs, but demand was intact.” Since then, the margins the company guided to (on an EBITDA basis, before depreciation) came in as promised at 15.0% and 19.3%, and the third, 21.6% for the third quarter, comes in early November. On August 26 it won a jury verdict in its patent case against competitor Voltage ($96 million in damages and a US sales ban on the products involved).

Fluence Energy. As set out in my September 17 company check, I will see whether its fiscal fourth-quarter results in November meet three conditions. The first is fourth-quarter revenue of at least $780 million. The second is output at its Houston plant. The third is next-year revenue guidance (the company’s own forecast) of at least $3 billion. If it misses any one of them, I will close the tracker and write a look-back piece.


All on one board

Line the companies up by when their profits arrive, and the ones with profits growing now are the four transformer makers, Bloom Energy, BHI, Constellation and Vistra for this year, OCI Holdings from the third quarter, and Hanwha Solutions from the fourth. Turbine profits are growing too, but market expectations are already ahead of them, in my view.

As I was finishing this piece on October 13 closing prices, the sell-off hit. On October 15 alone, Korea’s KOSPI fell 7.6%, and the Korean names in this piece dropped 6-16% in a single day.

The biggest change was in Korean transformers. HD Hyundai Electric, Hyosung Heavy Industries and Sanil Electric fell around another 15% over two days. Their profits are coming in now; only the price changed. Whether margins hold in the third quarter is the next check.

In the full research, I put all 18 companies on one matrix. The horizontal axis is how near and how certain the profits are; the vertical axis is the distance between today’s price and fair value. I also recalculated each company’s fair-value range at post-sell-off prices. The board looks quite different after the sell-off. Where the names whose volumes rose first, such as engine parts and heat recovery, landed on it, and which companies moved where, are in the original.


Closing

There are not many standout spots in power right now. New power plants will not add electricity until 2028 or later. Apart from the few companies turning existing orders into revenue, the only ways to add power quickly are engines and batteries. Among engine names, HD Hyundai Marine Engine is showing the most promise, and I intend to keep watching it.

Oddly, batteries have been in the news a lot lately. Long-term supply contracts keep coming, and I am hearing that rules on the origin of raw materials have buyers, not only in the US but even in China, looking for Korean materials.

Batteries, though, still depend on ESS demand to carry them. My next check will be on batteries, to see whether things have improved since my April ESS piece. If batteries do improve, a scenario could emerge where KOSDAQ, Korea’s growth-stock market, takes the baton.

In the same field, every crop has its own season.

If you came for the structure, this piece covers it: where the power gets stuck and where the money flowed first. The fair-value ranges for 18 companies and the post-sell-off matrix are in the full research below.

Ciao. 🌱

🌱 Growth Wave · Full Deep Dive

Sector Check: Power | The grid can’t wait, and the power plants are late

This is a summary. The full research, with fair-value ranges for 18 companies and the post-sell-off matrix, is for subscribers.Read the full research →


This newsletter is for informational purposes only and does not constitute investment advice or a recommendation to buy or sell any security. The author may hold positions in the securities discussed. Do your own research and consider your own circumstances before investing.